Define project scope
Outline objectives, deliverables, and limits of the project.
Create project timeline
Develop a schedule detailing the time frame for each task and phase.
Schedule regular team meetings
Establish routine check-ins to discuss progress and address issues.
Monitor project progress and adjust plans
Use tools to track milestones and adapt plans as necessary.
Risk management and mitigation strategies
Identify potential risks and create strategies to minimize their impact.
Identify user needs and requirements
Conduct surveys or interviews with target users to gather needs.
Analyze existing sign language learning applications
Review current applications for strengths and weaknesses.
Gather feedback from potential users
Engage with users for insights on desired features and ease of use.
Document findings
Compile collected data into a structured format for reference.
Create overall description
Provide a high-level overview of the system and its purposes.
Write problem statement
Define the problems the application aims to solve.
Define product perspective
Explain how the product fits within its environment and context.
Outline product functions
List functionalities the system must provide.
Detail user characteristics
Describe the target user profile, including skills and demographics.
Specify design and implementation constraints
Identify limitations such as technology, budget, and regulatory requirements.
Develop system features and functional requirements
Specify detailed features including operational requirements.
Conclude SRS document
Summarize the key elements of the SRS for approvals.
Define system architecture
Determine the structure of the system, including servers and client applications.
Develop user interface wireframes
Create basic sketches of interface layout to guide design.
Design database schema
Plan the structure of the database to store application data efficiently.
Implement authentication module
Build a secure login system for user accounts.
Implement translation service module
Develop functionality for translating text into sign language through avatars.
Implement avatar animation module
Create animated characters to demonstrate sign language.
Implement learning module management
Set up mechanisms to manage learning resources and content.
Develop test cases
Prepare various scenarios to verify system functionality.
Perform unit testing
Test individual components for expected performance.
Conduct integration testing
Ensure modules work together seamlessly.
Execute user acceptance testing
Gather user feedback to validate that the application meets requirements.
Prepare deployment plan
Draft a strategy for rolling out the application to users.
Deploy application to production
Launch the application for the end-users.
Monitor application performance
Use analytical tools to ensure the application runs smoothly post-launch.
Gather user feedback for future improvements
Post-launch, actively seek user input to refine the application further.
Phase 1: Project Management & Research
Duration: Days 1-12
Phase 2: SRS Development
Duration: Days 10-27
Phase 3: Design & Architecture
Duration: Days 28-40
Phase 4: Development
Duration: Days 41-80
Phase 5: Testing
Duration: Days 81-100
Phase 6: Deployment & Maintenance
Duration: Days 101-Ongoing
This WBS establishes a thorough framework along with a well-organized timeline for the various phases of the Sign Saathi project, ensuring systematic progress and clarity of each stage.